          p 355
        
        
          
            Chapter 5
          
        
        
          PolyLEVEL
        
        
          ®
        
        
          Polyurethane Foam and Resin
        
        
          
            APPENDIX 5B
          
        
        
          MODEL SPECIFICATIONS
        
        
          MODEL SPECIFICATION FOR
        
        
          POLYURETHANE VOID FILLING OR
        
        
          SOIL STABILIZATION APPLICATIONS
        
        
          
            1
          
        
        
          SCOPE
        
        
          1.1 The work consists of designing, furnishing, and installing single-part, high-density polyurethane
        
        
          material according to the project plans and this specification.
        
        
          1.2 The parties and contract terms referred to in this specification are as follows:
        
        
          1.2.1 The Owner is the person or entity that owns the facility or will own the facility once it is
        
        
          completed. The Owner may have contractual agreements with, and be represented by,
        
        
          other parties such as engineers, architects, or contractors that preform services under the
        
        
          direction of the Owner. Where Owner is used in the specification, it refers to the Owner or
        
        
          the Owner’s contracted representatives separate from the Installing Contractor.
        
        
          1.2.2 The Installing Contractor installs the polyurethane material and possibly performs other
        
        
          tasks associated with the project.
        
        
          1.2.3 The Plans refer to the contract documents; including but not limited to the drawings and
        
        
          specifications for the project.
        
        
          1.3 The work may include void filling, stabilizing loose or sandy soil, or undersealing pavement and
        
        
          faulted joints.
        
        
          1.4 The Owner will provide suitable access to the construction site for the Installing Contractor’s
        
        
          personnel and equipment.
        
        
          1.5 Unless otherwise noted, the Installing Contractor shall provide all labor, tools, equipment, and
        
        
          material necessary to accomplish the work.
        
        
          1.6 Unless specifically noted otherwise in the contract documents, the Owner will remove and
        
        
          replace structures, utilities, or other surficial improvements in the work area as necessary to
        
        
          facilitate the work.
        
        
          1.7 The Owner will be responsible for overall construction oversight to preclude the development of
        
        
          unsafe conditions.
        
        
          1.8 The Owner will be responsible for any soil density testing subsequent to the polyurethane
        
        
          injection, unless otherwise noted.
        
        
          1.9 The work does not include and post-installation monitoring unless specifically noted otherwise
        
        
          in the contract documents.
        
        
          
            2
          
        
        
          APPROVED POLYURETHANE MANUFACTURERS
        
        
          2.1 Foundation Supportworks
        
        
          ®
        
        
          , Inc., 12330 Cary Circle, Omaha, NE 68128; Phone: (800) 281-8545;
        
        
          Fax (402) 393-4002.